Hello,
I'm currently working with an IRB 920 and an OmniCore C30. In RobotStudio, I want to simulate two conveyors. I managed to set up the first conveyor successfully, it works fine. However, when I try to configure the second conveyor, I can't create a connection; the option is greyed out.
From what I understand, the mechanical unit associated with the first conveyor (CNV1) is properly created in the controller. However, I can’t figure out how to create a second mechanical unit, for example, CNV2, that I could link to the second conveyor.
Is this an option I should have selected earlier? Thank you!


Comments
2 comments